Does Your Secondary Containment Need a Liner? What the EPA SPCC Rule Asks of Containment Floors and Walls

The federal SPCC rule does not require a liner. It requires containment that holds oil until cleanup, walls and floor included, and leaves the method to the owner or operator and whoever certifies the Plan: a Professional Engineer, or the owner for a qualified facility. This post covers what the rule says, what EPA tells its inspectors to look for, and where a coated liner fits.

ByA-1 Roofing

In short

The EPA's SPCC rule does not require a liner. It requires secondary containment, walls and floor included, that holds discharged oil until it is cleaned up, and it leaves the design to the owner or operator and the Professional Engineer who certifies the Plan, or to the owner where a small qualified facility self-certifies. A coated liner is one way to make a cracked or porous concrete area meet that standard.

Which facilities does the SPCC rule cover?

The Spill Prevention, Control, and Countermeasure rule is federal: 40 CFR part 112. It applies to a non-transportation facility that stores, uses or handles oil and, because of where it sits, could reasonably be expected to discharge harmful amounts of oil into navigable waters or onto adjoining shorelines (40 CFR 112.1(b)).

Small facilities are exempt. Under 40 CFR 112.1(d)(2), the rule does not apply where aboveground oil storage totals 1,320 U.S. gallons or less, counting only containers of 55 gallons or more, and completely buried storage totals 42,000 gallons or less. Both limits must be met, and the paragraph lists the containers left out of the count (see the FAQ).

Do a dike or a farm change whether the rule applies?

Containment does not take a facility out of the rule. When deciding whether a facility could reach navigable waters, 40 CFR 112.1(d)(1)(i) says to consider only its location and to ignore manmade features such as dikes.

Farms have separate thresholds under the 2014 Water Resources Reform and Development Act. EPA's April 2015 fact sheet (a legacy benchmark) says a farm with less than 2,500 gallons of aggregate aboveground oil storage needs no SPCC Plan, and a farm with up to 20,000 gallons, no tank over 10,000 gallons and no reportable discharge history may self-certify its Plan.

What does the SPCC rule require of secondary containment?

Two sections do most of the work. The general requirement, 40 CFR 112.7(c), says the entire containment system, including walls and floor, must be capable of containing oil so that a discharge does not escape before cleanup occurs. It lists the methods a facility may use, starting with dikes, berms or retaining walls sufficiently impervious to contain oil, then curbing, drip pans, sumps, and other options.

For containment that is not bulk storage, such as transfer areas and oil-filled equipment, 112.7(c) sizes it to the typical failure mode and the most likely quantity of oil, not the full tank.

What does it require around bulk storage tanks?

For bulk storage containers at onshore facilities other than oil production facilities, 40 CFR 112.8(c)(2) adds a size: secondary containment for the entire capacity of the largest single container, plus sufficient freeboard to contain precipitation. It also says diked areas must be sufficiently impervious to contain discharged oil, and that dikes, containment curbs and pits are commonly used for the purpose.

Neither section requires a liner on the containment area. A liner or coating is one way to make a dike, curb or pit sufficiently impervious.

What does sufficiently impervious mean?

EPA answers this in its SPCC Guidance for Regional Inspectors, the manual its own inspectors work from. EPA says the guidance does not impose legally binding requirements; where it says should, it is recommending, not requiring. Chapter 4, dated December 16, 2013, says the rule does not specify permeability, hydraulic conductivity or retention-time criteria, and that sufficiently impervious does not necessarily mean indefinitely impervious.

The test is time. Containment counts as sufficiently impervious if it holds the oil long enough for cleanup to happen before the oil reaches navigable waters or adjoining shorelines. The owner or operator and/or the certifying engineer decide how to meet that, based on good engineering practice, the facility layout and the product stored.

Does the stored product change what counts as impervious?

The product matters. The guidance gives an example: compacted local soil may be suitable to hold a viscous product such as liquid asphalt cement but may not be suitable for gasoline. It also says permeability through the wall, or through the joint where wall meets floor, must be carefully evaluated.

In a concrete containment area, EPA's guidance points to that joint, to cracks, to porous block walls and to penetrations as the places to evaluate closely.

Is 110 percent of the largest tank the federal rule?

No. The federal rule asks for the entire capacity of the largest single container plus sufficient freeboard for precipitation, and it does not put a number on the freeboard. EPA's inspector guidance says so directly: the SPCC rule does not specify a volume amount to account for precipitation, giving 110 percent of capacity as the example of what it does not set.

The 110 percent figure comes from elsewhere. The same guidance calls it a rule of thumb that may be an acceptable design criterion in many situations, and notes that aboveground storage tank regulations in many states require containment sized for at least 110 percent of the largest tank. It also warns that in some situations 110 percent may not hold the rain from a storm.

What about the 25-year storm?

In the preamble to its 2002 amendments, EPA said it believed the proper standard for sufficient freeboard was the precipitation from a 25-year, 24-hour storm (67 FR 47117, July 17, 2002), but it did not make that a requirement. The guidance tells inspectors that standard is not enforceable, and that the owner or operator, or the certifying engineer, may want to consider it where the rainfall data exist.

Outside South Dakota, the size a given area needs is set by the facility's SPCC Plan and whatever state rule applies.

What does South Dakota require of containment?

In South Dakota the state sets the number. Regulated aboveground tank systems must use one or more of three options: performance standards with overfill control, secondary containment, or release detection (ARSD 74:56:03:04).

Where secondary containment is the choice, ARSD 74:56:03:11 requires containment for new tank systems to hold 110 percent of the largest tank at the facility, with an impermeability of at least 10⁻⁶ centimeters per second for the life of the system. Native soils, clays, bentonites or an artificial material equivalent to 60-mil high-density polyethylene or greater may be used. The containment must be compatible with what is stored and designed to control storm water.

The plans and specifications go to the department for approval at least 30 days before construction, and the installer certifies the work on the department's certification of compliance form (ARSD 74:56:03:03).

What do EPA inspectors look for in a containment area?

EPA's inspector guidance lists what to check on a dike, berm or other engineered containment system. The items include capacity to contain oil as good engineering practice and the rule require; cracks in containment system materials, naming concrete, liners, coatings and earthen materials; discoloration; spilled or leaked material; corrosion; erosion; the operational status of drain valves; dike or berm permeability; debris; the level of precipitation in the diked area and available capacity versus design capacity; and the pipes, inlets and drainage around and beneath the containers.

Liners and coatings are on that list by name, so the inspector checks a liner for cracks like any other containment material.

The guidance also says the owner or operator should monitor the containment to make sure it stays impervious to oil, and that repairs to excavations or other penetrations through it need to follow good engineering practice.

Can rainwater be drained out of a lined containment area?

Only under conditions. 40 CFR 112.8(c)(3) bars draining uncontaminated rainwater from a diked area into a storm drain or open water, bypassing the facility's treatment system, unless the facility normally keeps the bypass valve sealed closed, inspects the retained rainwater to make sure it will not cause a discharge, opens and reseals the valve under responsible supervision, and keeps adequate records of each drainage.

That matters for a liner because the rainwater sits on it. A lined area that holds water between drainings needs a liner the manufacturer rates for standing water. For onshore facilities, 40 CFR 112.8(b)(2) also calls for manual, open-and-closed drain valves, not flapper-type valves, so the liner has to be detailed around a valve the facility can keep sealed.

When does a coated liner make sense for secondary containment?

When the containment structure is in the right place and the right size but its surface cannot be trusted to hold oil until cleanup: concrete that has cracked or spalled, a block wall, a wall-to-floor joint that has opened, or penetrations that were never sealed.

A liner job usually follows the order of those weak points. Cracks and spalls are repaired first so the liner bonds to sound concrete. Corners, sumps and pipe penetrations are detailed next. Then the field coat goes on in a system the manufacturer rates for what the area holds, by its data sheet for chemical and immersion exposure.

A liner does not fix the wrong size. If the area cannot hold the largest container plus freeboard, the answer is a taller wall or a bigger area, and that is a design question for whoever certifies the Plan.

What liner work has A-1 done?

A-1's liner work to date is one job, and it was not SPCC oil containment. Years ago, A-1 lined the floor of a large sewage tank at a newly built methane generation research facility. The liner was VFI-425, a polyurea hybrid, at 90 mils. Prep was grinding, cleaning and priming; the job took four days. An engineer was on site. The facility was a prototype.

VFI polyurea is the only system A-1 has used for containment. A-1 has equipment for other liners but no market for them yet. It holds no South Dakota DANR certification for this work, and on containment jobs it usually works with an engineer.

Kent Sybesma, A-1's Director of Operations, on why concrete needs a liner: "Concrete does 2 things, It gets hard and it cracks. Fluid applied liners remain flexible and conform to any surface contour easily and efficiently."

What if containment is not practicable?

The rule allows for it, with conditions. If containment is not practicable, 40 CFR 112.7(d) says the Plan must clearly explain why; for bulk storage containers, the facility must conduct periodic integrity testing of the containers and periodic integrity and leak testing of the valves and piping; and, unless it has submitted a facility response plan, the Plan must include an oil spill contingency plan and a written commitment of manpower, equipment and materials.

A self-certified Plan cannot make that call on its own. Under 40 CFR 112.6, a Tier II qualified facility's Plan may not include an impracticability determination unless a Professional Engineer has reviewed and certified it in writing. Lining a cracked area is often simpler than proving containment cannot be built.

What should the SPCC Plan say about a liner?

It should describe it. EPA's guidance quotes the 2002 preamble: a complete description of how secondary containment is designed, implemented and maintained to meet the sufficiently impervious standard is necessary (67 FR 47102, July 17, 2002). It adds that the determination of imperviousness should be verified by a Professional Engineer and documented in the Plan.

For a liner, that means the Plan should be able to name the system, the substrate preparation, the areas it covers, including the joints and penetrations, and how it is inspected and repaired. A contractor's product data and installation record are the raw material for that description.

What should you get from the liner installer?

Before the area goes back into service, ask the installer for the product data sheets, the thickness readings and photos of the joints and penetrations, so the Plan can describe what was built.

If a containment area at your facility has cracked concrete, open joints or unsealed penetrations, ask A-1 to look at it before your next Plan review.

What does this post not tell you?

This post summarizes the federal SPCC rule, 40 CFR part 112, as published in the eCFR and checked on November 11, 2026, and EPA's SPCC Guidance for Regional Inspectors, Chapter 4, dated December 16, 2013, which is more than 18 months old and is a legacy benchmark. It covers South Dakota's aboveground tank rule (ARSD chapter 74:56:03); other state and local rules may add requirements this post does not cover, and other federal rules may apply to hazardous materials that are not oil. Whether a facility is covered, what size its containment must be and whether a given surface is sufficiently impervious are decisions for the owner or operator and whoever certifies the SPCC Plan. This post is not legal or engineering advice, and A-1 Roofing does not guarantee that any liner will satisfy a regulator.

Questions owners ask next

Does a containment area inside a building need freeboard for rain?
EPA's inspector guidance says that when secondary containment is inside a building, freeboard calculations for precipitation are typically not applicable. The capacity of the largest container still applies. The engineer certifying the Plan may count the building's walls and drainage as containment, but the guidance says the area must not have open floor drains or an automated sump pump unless the drainage is equipped to treat a discharge, and doorways and other openings must be considered too.
What storage is left out of the 1,320-gallon count?
Under 40 CFR 112.1(d)(2), the aggregate aboveground capacity excludes permanently closed containers, motive power containers, hot-mix asphalt containers, heating oil containers used solely at a single-family residence, pesticide application equipment and related mix containers, and milk and milk product containers and their piping. Containers under 55 gallons are not counted.
Who certifies an SPCC Plan?
40 CFR 112.7 refers to a Plan certified by a licensed Professional Engineer under 40 CFR 112.3(d), and to qualified facilities meeting the criteria in 40 CFR 112.3(g), which have their own certification provisions. A qualified facility has 10,000 gallons or less of aboveground oil storage and no single discharge over 1,000 gallons, or two over 42 gallons in a 12-month period, in the three years before the Plan is certified (40 CFR 112.3(g)). Whoever certifies the Plan, the engineer or the owner of a qualified facility, makes the call on whether containment is sufficiently impervious. The liner installer supplies the product data and installation record.
What about tanks that hold hazardous waste instead of oil?
Those fall under a different federal rule. Under RCRA, 40 CFR 264.193(e)(1) requires an external liner around a hazardous-waste tank to hold 100 percent of the largest tank, keep out precipitation unless there is room for a 25-year, 24-hour storm, and be free of cracks or gaps.
Can bare soil serve as secondary containment?
Sometimes. EPA's guidance says native soil such as clay may be found sufficiently impervious in certain locations, but that good engineering practice would generally not allow native soil alone when the soil is not uniform, and that some states restrict soil as containment.

Related on this site

Sources

  1. eCFR — 40 CFR 112.1, General applicability (checked November 11, 2026; last amended April 18, 2011): who is covered, the 1,320-gallon and 42,000-gallon exemptions
  2. eCFR — 40 CFR 112.7, General requirements for SPCC Plans (checked November 11, 2026): walls and floor capable of containing oil, prevention systems
  3. eCFR — 40 CFR 112.8, SPCC Plan requirements for onshore facilities (checked November 11, 2026; last amended December 5, 2008): largest container plus freeboard, sufficiently impervious, rainwater drainage
  4. eCFR — 40 CFR 112.3 (checked November 11, 2026): qualified facilities, Tier I and Tier II
  5. eCFR — 40 CFR 112.6 (checked November 11, 2026): qualified facility Plans, impracticability needs PE certification
  6. eCFR — 40 CFR 264.193 (checked November 11, 2026): containment for hazardous-waste tank systems
  7. South Dakota ARSD 74:56:03:11, Secondary containment required for new AST systems (current; 14 SDR 76, effective November 29, 1987, amended 1991): 110%, 10^-6 cm/s, 60-mil HDPE equivalent, plan approval 30 days before construction
  8. South Dakota ARSD 74:56:03:04, General requirements for AST systems
  9. South Dakota ARSD 74:56:03:03, Certification of compliance with requirements
  10. US EPA — WRRDA fact sheet for farms (April 24, 2015, legacy benchmark)
  11. US EPA — SPCC Guidance for Regional Inspectors, Chapter 4: Secondary Containment and Impracticability (December 16, 2013, legacy benchmark)
  12. US EPA — SPCC Guidance for Regional Inspectors (all chapters)